Improving water quality in the Ganga has been an important aim in India. Since June 2014, thousands of crores have been allocated to improve water quality in the Ganga. Improvements have been made in sewage treatment, sewerage networks, reducing industrial pollution and riverfront improvement. The Ganga passes through many important cities in Uttar Pradesh.
A recent investigation by Bloomberg has raised concerns about improvements in water quality in the Ganga. Analysis of satellite imagery along 2000km of the river, independent water sampling and on the ground, reporting has indicated that in many parts of the river, water quality is poor. Water sampling near Kanpur and Varanasi has raised concerns about contamination. The Centre responded to this report, indicating that with a river spanning 2500km through 5 states, it is difficult to gain an accurate picture of water quality from limited samples and indicators. They indicated that in some locations water quality has improved, and that improvements have been made in treating sewage and reducing industrial pollution. However, in Uttar Pradesh, it should be considered whether investments have been effective in improving water quality.
Investment in Uttar Pradesh
No specific amounts of money were allocated to each state under the Namami Gange scheme. Funding was allocated to projects, and total expenditure in each location was determined.
Within Uttar Pradesh, the National Mission for Clean Ganga (NMCG) invested around 7981.08crore in projects between 2014-15 and 15th March 2026.
In 2014-15 74.58 crore was invested. By 2016-17, this increased to 585.15 crore, and by 2019-20 it had increased further to 876.68. A significant increase occurred in 2024-25 with 1225.05 crore being invested. In 2025-26 1130.31 crore has been invested (up to 15th March 2026).
These figures indicate money given to implementing bodies to invest in projects in this location. This does not indicate total expenditure by the Uttar Pradesh government, or value of sanctioned projects.
In September 2026, the NMCG provided a progress report. In Uttar Pradesh, 81 projects have been sanctioned to improve Sewage Infrastructure. However, only 6601.30 crore has been invested in these projects, including state funding. This means that only 41% of the total project cost has been invested in. It may be interesting to consider the difference in costs here. Many projects still seem to be being constructed or are in the tendering phase.
UP’s Budget for Namami Gange
Within the 2026-27 Uttar Pradesh Budget, emphasis was placed on the Namami Gange and rural water supply department. The state government has proposed to allocate approximately 22676 crores in this section.
However, this is not solely to improve water quality in the Ganga. In the same budget, approximately 22452 crores have been proposed to be invested in various elements of the Jal Jeevan Mission. Therefore, it should not be assumed that 22676 crore is solely for rejuvenating the river.
Within the budget speech, 74 Sewage Projects have been sanctioned to prevent pollution and untreated effluent entering the river. 41 have been completed and operational, however, others are still under construction.
However, the NMCG project report from September 2026 highlights that in Uttar Pradesh, there are 81 Sewage Infrastructure projects. Of these, 53 have been completed, 25 are under construction, and 3 are in the tendering process.
Although these reports are from different times and categorise projects differently, they do suggest that many sewage projects still need to be completed.
Within these 81 projects, the total project cost is 16051.59 crore. The total capacity for treatment is 2423.13 MLD. By September 2026, 1302.01 MLD of capacity has been created. In addition, 1817.98km of sewerage has been installed, compared to the planned total of 1957.97km. Although there has been an increase in infrastructure, a large difference remains between planned and achieved capacity.
Challenges in reducing sewage
The Uttar Pradesh government’s Namami Gange dashboard provides further information on this.
In urban areas of Uttar Pradesh, approximately 5500 MLD of sewage is generated. The installed capacity of 157 Sewage Treatment Plants means that 4729.24 MLD of sewage can be treated. Out of this, 988 MLD of capacity is provided by 45 plants within the National Ganga River Basin Authority/Namami Gange programme. The remaining capacity has been developed within other schemes, such as previous Ganga Action Plans and urban development schemes.
Within different schemes, 50 Sewage Treatment Plants are currently under construction. Combined, they have a capacity of 1609.1 MLD. Of these, 39 plants (1249.1 MLD) fall under the Namami Gange scheme. In addition to this, 4 Namami Gange plants (proposed capacity 502 MLD) are in the planning stage.
These figures must be read while keeping in mind that the installed capacity does not necessarily directly relate to the amount of sewage treated. Even if plants exist and are operational, the efficiency of treating sewage will depend on the extent of sewerage connecting homes and drains to the plant, volume of sewage and quality of treatment. The next stage of this scheme must consider that merely adding more plants will not solve the issue if sewage continues to enter the river via drains that are not connected to any treatment plant.
Industrial Pollution in Kanpur and Varanasi
Industrial pollution is also a key factor in determining the status of the Ganga’s water quality in Uttar Pradesh. In Kanpur, the tannery industry majorly contributes to the industrial effluent entering the river.
The government highlighted measures to reduce industrial pollution in this area. A Common Effluent Treatment Plant (20 MLD) was commissioned in Jajmau for the tannery area and the Sisamau drain has been intercepted, so that untreated sewage is no longer being discharged into the Ganga.
In the Ganga basin, the industrial compliance rate has increased from 39% (2017) to 86% (2025). In addition, the amount of pollution in terms of Biochemical Oxygen Demand (BOD) from industries has decreased from 26 tonnes per day to 12 tonnes per day.
In this context, it becomes important to consider which industries are continuing to fail to meet discharge standards, how often they are being inspected, and how effective monitoring is in ensuring improvement after corrective measures have been made.
Improvements in water quality
Comparison of polluted sections in 2018 and 2025 by the Central Pollution Control Board provides more direct evidence. Earlier, a polluted section was identified in Uttar Pradesh between Kannauj and Varanasi. In 2025, a polluted section has been identified between Bijnor and Tarighat. Therefore, partial improvement has been made.
Within the reply from the Ministry of Jal Shakti (February 2026), it was stated that, based on median data between January and August 2025, pH and dissolved oxygen levels met bathing standard in all monitoring locations along the Ganga.
However, in 3 sections in Uttar Pradesh, biochemical oxygen demand (BOD) levels exceeded bathing standards. These were between Farrukhabad and Purana Rajapur (Kanpur), Dalmau (Raebareli) and downstream Mirzapur and Tarighat (Ghazipur). It is important to note that although pH and dissolved oxygen levels meet bathing standards, this does not necessarily mean that water quality is satisfactory. BOD levels, faecal contamination and industrial pollutants must also be monitored.
Based on this data, the water quality in the Ganga in Uttar Pradesh appears to be mixed. There has been improvement in some sections. However, pollution still exists in some areas.
Next steps – ensuring accountability
The debate in November has highlighted that financial investment, infrastructure development and environmental improvements do not always match up.
Sewage treatment capacity has been increased, investment in sewerage infrastructure has occurred, industrial effluent treatment has been supported, as well as riverfront and ecological projects. 33024 hectares of afforestation has been completed in the main stem of the Ganga, costing approximately 414 crores, as part of the wider rejuvenation efforts.
However, to ensure long term improvement in water quality, it is important to ensure that improvements in infrastructure are effective, untreated sewage is prevented from entering the river, and industrial pollution is consistently monitored.
In Uttar Pradesh, it would be useful to consider not only how many projects have been completed, or how much money has been invested, but rather how much sewage is being generated, how much is reaching treatment plants, and how much is being effectively treated. In addition, it would be useful to see if water quality in these locations has improved over time.
Whilst it may have improved in some monitored locations, polluted sections still exist in Uttar Pradesh. Therefore, in order to measure the success of the Namami Gange initiative, the quality of water in the Ganga should be considered, rather than the number of treatment plants or crores invested.